Propping and Shoring for Structural Alterations

Most structural alterations involve a period where loads are carried temporarily. That period is where most problems occur on site.
This guide covers how propping and shoring is planned for typical alterations.
Why the sequence matters
A wall opening may need props, needles, padstones and a steel beam installed in a set order. Skipping or reordering steps can overload brickwork or floors.
Supporting floors above
Props must bear on a floor or foundation that can take the load, so the engineer checks the ground and any floors below as well as the structure above.
Needles and temporary beams
Needles transfer load to props while a permanent beam is built in. Their size and spacing are designed, not guessed, and depend on the wall above.
Working near neighbours
On terraces and semi-detached houses, party walls and adjoining owners are affected. Share designs early and monitor cracks if the surveyor requires it.
Removal and making good
Props come out only when the permanent structure has gained enough strength and been inspected. Then walls are made good and packed properly.
Related guides: Structural engineering and project management together, What construction project management consultancy involves, Managing building control approvals, all our guides.
Talk to Graal
Working on a project anywhere in London and need structural input? Graal Structural Engineering supports contractors, developers and architects with structural design, calculations, temporary works design and project management. Call 07737188754 or send your drawings through our contact form and we will come back to you with what is needed and how long it is likely to take.





Comments